The project manager's estimate of the remaining cost to finish a job. It drives estimate at completion, percent complete, earned revenue, and projected margin, so its accuracy and freshness matter.

Plan your metrics

What it is

Cost to complete (also called estimate to complete) is a forecast, not an accounting number. The PM builds it from remaining quantities, open commitments, and labor still needed.

This page covers the number itself and two ways to check it: forecast age (days since last update) and forecast change (how much it moved since last month).

Why operators track it

  • Everything downstream depends on it. Under cost-to-cost, percent complete is cost to date divided by cost to date plus cost to complete.
  • Understated forecasts get caught. Understating remaining cost raises percent complete and earned revenue until the cost catches up, and sureties read the trend for this (Surety Bond USA).
  • Stale forecasts hide problems. A forecast not updated for months makes a troubled job look stable.
  • It is where PM judgment enters the numbers. Tracking it by PM shows whose forecasts move most.

How it is calculated

Cost to complete = estimate at completion − cost to date

  • A bottom-up forecast by cost code is stronger than budget minus cost to date.
  • Forecast age = as-of date − date the forecast was last saved.
  • Forecast change = this month's estimate at completion − last month's.

Worked example

Job 2417 has $910,000 of cost to date and a forecast of $420,000 to complete, updated three days ago. Job 2431's forecast of $310,000 was last updated 63 days ago and equals its remaining budget.

Estimated cost to complete, with forecast ageJob 2417$420,000updated Oct 28 (3 days ago)Job 2420$470,000updated Oct 30 (1 days ago)Job 2431$310,000updated Aug 29 (63 days ago)Estimate at completion = cost to date + cost to complete. Job 2417: $910,000 + $420,000 = $1,330,000.Job 2431's forecast is 63 days old. Its percent complete, earned revenue, and margin all depend on a numberno one has confirmed since August.
Example data Red marks a forecast older than one month-end close. The number may be right; the problem is that no one has checked it.

How to read it

  • Check age before reading the number. An old forecast is a question, not an answer.
  • Budget minus cost is not a forecast. If cost to complete always equals remaining budget, no one is forecasting.
  • Large swings late in the job suggest earlier forecasts were not realistic.
  • Compare to committed cost. Remaining cost should at least cover open commitments.
  • We do not publish a benchmark for forecast accuracy.

Definitional choices and common pitfalls

  • Bottom-up or default. Decide whether jobs with no PM update default to remaining budget, and flag them when they do.
  • Level. By cost code or job total. Cost code is better for review; job total is enough for WIP.
  • Update cadence. Monthly at close is common. Define what counts as stale.
  • Negative remaining budget. If cost to date exceeds budget on a code, the forecast must still be at least zero.

How different roles use it

Role How they use it
Project manager Updates cost to complete by cost code every month.
CFO / controller Checks forecast age and large changes before closing the WIP.
Owner / CEO Asks about jobs whose forecast jumped.
Operations / superintendent Supplies remaining quantities and crew needs from the field.

Questions it answers

  • Which forecasts are out of date?
  • Which jobs' forecasts moved the most this month?
  • Are any forecasts just budget minus cost?
  • Does remaining cost cover open commitments?

How to present it in a report

  • One row per job: cost to date, cost to complete, estimate at completion, change vs last month, and last updated date.
  • Flag stale forecasts and forecasts equal to remaining budget.
  • Drill down to cost code.
Customer report mockupExample data
Forecast reviewOctober 2026 close
Forecasts current2 of 3within 31 days
Stale1job 2431
EAC change, job 2417+$16,000vs September
JobPMCost to dateCost to completeEACUpdatedFlag
2431A. Diaz$1,620,000$310,000$1,930,000Aug 29Stale, equals remaining budget
2417J. Moore$910,000$420,000$1,330,000Oct 28
2420J. Moore$240,000$470,000$710,000Oct 30

Data you need

Fields

Field What it means Example value
Job and cost code Where the forecast applies Job 2431, 03-300 concrete
Cost to date Posted cost $1,620,000
Cost to complete PM's remaining cost forecast $310,000
Forecast saved date When the PM last saved it Aug 29
Forecast by Who saved it A. Diaz
Remaining budget Revised budget minus cost to date $310,000

What the raw data looks like

Example data A few rows as they might come out of the source system.

Job Cost to date Cost to complete Remaining budget Saved By
2417 $910,000 $420,000 $370,000 Oct 28 J. Moore
2420 $240,000 $470,000 $478,000 Oct 30 J. Moore
2431 $1,620,000 $310,000 $310,000 Aug 29 A. Diaz

Where this data usually lives

  • Construction ERP and accounting holds job cost, budgets, billing, AP, and AR. For example: Sage 300 Construction and Real Estate, Viewpoint Vista (Trimble), and Foundation. Some smaller contractors use general accounting software such as QuickBooks with jobs set up as projects.
  • Project management often holds change orders, commitments, and project documents. For example: Procore.
  • Spreadsheets often hold forecasts, logs, or the report itself.

The same field can live in more than one system. Agree with the customer which one is the source of truth.

Common data gaps and traps

  • No saved date. If the forecast has no timestamp, age cannot be measured. Audit logs may help.
  • Forecasts in spreadsheets. The real forecast may never reach the system.
  • Overwritten history. Without monthly snapshots, forecast change cannot be calculated.
  • Default to remaining budget. Some systems fill it in automatically, which looks like a forecast but is not.

FAQ

Is cost to complete the same as remaining budget?
No. Remaining budget is budget minus cost. Cost to complete is the PM's forecast of what is actually left.
How often should it be updated?
Commonly every month before close. Define your own staleness rule.
Why does it change earned revenue?
Under cost-to-cost, percent complete uses estimated total cost, so a change in the forecast changes earned revenue.
For your data teamFormula variants, tables, SQL sketch, and dashboard spec

Formula details

cost_to_complete = pm_forecast (bottom-up, by cost code)
eac              = cost_to_date + cost_to_complete
forecast_age     = :as_of - forecast_saved_at
forecast_change  = eac[now] - eac[prev]
defaulted        = cost_to_complete = revised_budget - cost_to_date

Worked example detail

Job EAC Age (days) Defaulted?
2417 $1,330,000 3 No
2420 $710,000 1 No
2431 $1,930,000 63 Yes

Tables and fields

Table Fields Notes
cost_forecasts job_id, cost_code, period, cost_to_complete, saved_at, saved_by Keep every period
job_costs job_id, cost_code, amount, posted_at
budgets job_id, cost_code, revised_budget

SQL sketch

SELECT f.job_id, SUM(f.cost_to_complete) AS ctc, :as_of - MAX(f.saved_at) AS forecast_age,
  BOOL_AND(f.cost_to_complete = b.revised_budget - c.ctd) AS defaulted
FROM cost_forecasts f JOIN budgets b USING (job_id, cost_code)
JOIN (SELECT job_id, cost_code, SUM(amount) ctd FROM job_costs GROUP BY 1,2) c USING (job_id, cost_code)
WHERE f.period = :period GROUP BY f.job_id;

Build spec

Copy this into a ticket. It lists the grain, inputs, logic, and edge cases.

metric: construction.cost_to_complete
grain: one row per job per cost code per period
inputs:
  - cost_to_date
  - cost_to_complete
  - saved_at
  - revised_budget
logic:
  - eac = cost_to_date + cost_to_complete
  - age = as_of - saved_at
  - flag stale if age > cadence
  - flag defaulted if ctc = remaining budget
edge_cases:
  - ctc < 0: set to 0 and flag
  - no forecast saved: show as missing, do not default silently
  - closed job: ctc = 0

As a dashboard card

  • Table of jobs with cost to complete, age, change, and flags; KPI for count of stale forecasts.

Common mistakes

  • Treating remaining budget as a forecast.
  • Not timestamping forecasts.
  • Letting negative cost to complete through.