Construction · Field operations

Labor productivity by cost code

How many labor hours the work installed should have taken, compared with the hours actually used, by cost code. It shows where labor is running over before the cost report does.

Plan your metrics

What it is

Estimates price labor as hours per unit of work, such as hours per square foot of slab. In the field, crews record hours by cost code and foremen report quantities installed.

Earned hours are the hours the installed quantity was worth under the estimate. Comparing them with actual hours gives a productivity factor.

Why operators track it

  • Labor is hard to predict. Material prices are usually fixed by purchase order; labor depends on the field.
  • Earlier than cost variance. Hours and quantities can be reported daily or weekly; the cost report lags.
  • Better forecasts. The current rate on a cost code is a basis for the remaining hours forecast.
  • Better bids. Actual rates on finished jobs feed future estimates.

How it is calculated

Productivity factor = earned hours ÷ actual hours

  • Earned hours = budgeted hours × (quantity installed ÷ budgeted quantity).
  • Above 1.0 is better than estimate; below 1.0 is worse.
  • An alternative is units per hour: quantity installed ÷ actual hours, compared with the estimated rate.

Worked example

On job 2420, the slab on grade code has 1,300 budgeted hours for 26,000 square feet. Crews have installed 13,520 square feet (52%), worth 680 earned hours, but used 1,000 hours. The productivity factor is 0.68.

Job 2420 concrete: productivity factor by cost codeFormwork0.871,300 earned hrs ÷ 1,500 actualRebar1.03620 earned hrs ÷ 600 actualSlab on grade0.68680 earned hrs ÷ 1,000 actualFinishingnot started1.0 = as estimatedProductivity factor = earned hours ÷ actual hours. Earned hours = budgeted hours × percent of quantity installed.Slab on grade: 1,300 budget hrs × 52% installed = 680 earned, against 1,000 actual. The crew is at 0.68.
Example data Below 1.0 means the crew is using more hours than the estimate allowed for the quantity installed.

How to read it

  • Look at the trend, not one week. Start-up on a new code is often slow.
  • Quantities drive the answer. If foremen do not report quantities, the metric cannot be trusted.
  • Combine with remaining hours. A low factor early on a large code is a forecast problem.
  • Productivity varies by trade, crew, and site, so we do not publish a benchmark.

Definitional choices and common pitfalls

  • Hours basis. Use hours, not labor dollars, so wage changes do not distort it.
  • Quantity source. Foreman daily reports, survey, or schedule of values. Pick one per cost code.
  • Rework. Decide whether rework hours stay on the original code or go to a rework code.
  • Period. Cumulative to date vs this week. Show both.

How different roles use it

Role How they use it
Operations / superintendent Reviews productivity by crew and cost code weekly.
Project manager Uses current rates to forecast remaining labor.
Estimator Updates unit rates from finished jobs.
Owner / CEO Sees which jobs and trades are running behind the estimate.

Questions it answers

  • Which cost codes are using more hours than estimated?
  • Is productivity improving week to week?
  • How many hours will it take to finish at the current rate?
  • Which crews are fastest on similar work?

How to present it in a report

  • One row per cost code: budget hours, percent installed, earned hours, actual hours, and factor.
  • Color factors above and below 1.0.
  • Weekly trend line of the factor for large codes.
  • Projected hours at completion at the current rate.
Customer report mockupExample data
Labor productivityJob 2420 · week ending Oct 17, 2026
Overall factor0.843 active codes
Hours over earned500to date
Lowest codeSlab on grade0.68
Cost codeBudget hrs% installedEarned hrsActual hrsFactor
03-310 Slab on grade1,30052%6801,0000.68
03-110 Formwork1,80072%1,3001,5000.87
03-210 Rebar90069%6206001.03

Data you need

Fields

Field What it means Example value
Job and cost code Where hours and quantities are tracked Job 2420, 03-310 slab on grade
Budgeted hours Hours in the estimate 1,300
Budgeted quantity and unit Quantity in the estimate 26,000 SF
Quantity installed Reported by the foreman 13,520 SF
Actual hours From timecards 1,000
Crew and date Who and when Crew 4, Oct 14

What the raw data looks like

Example data A few rows as they might come out of the source system.

Date Job Cost code Crew Hours Quantity Unit
Oct 13 2420 03-310 Crew 4 64 820 SF
Oct 14 2420 03-310 Crew 4 72 910 SF
Oct 14 2420 03-110 Crew 2 40 1,150 SFCA
Oct 15 2420 03-210 Crew 2 32 3.1 TON

Where this data usually lives

  • Payroll and time tracking hold hours and labor cost by job and cost code, sometimes from a field time app.
  • Field reporting (daily logs, foreman reports) holds quantities installed and site events.
  • Construction ERP and accounting holds job cost, budgets, billing, AP, and AR. For example: Sage 300 Construction and Real Estate, Viewpoint Vista (Trimble), and Foundation. Some smaller contractors use general accounting software such as QuickBooks with jobs set up as projects.
  • Spreadsheets often hold forecasts, logs, or the report itself.

The same field can live in more than one system. Agree with the customer which one is the source of truth.

Common data gaps and traps

  • Quantities not reported. Hours come from payroll automatically; quantities need a foreman to enter them.
  • Hours on the wrong code. Crews may charge time to whatever code is convenient.
  • Different units. Estimate and field may use different units for the same work.
  • Time tracking outside the ERP. Field apps may hold hours that reach payroll but not job cost by code.

FAQ

What is a productivity factor?
Earned hours divided by actual hours. 1.0 means the crew is working at the estimated rate.
Why hours and not dollars?
Hours remove the effect of wage rates and overtime premiums.
What if quantities are not tracked?
Then productivity cannot be measured directly. Percent complete by cost code from the PM is a weaker substitute.
For your data teamFormula variants, tables, SQL sketch, and dashboard spec

Formula details

pct_installed       = qty_installed / budget_qty
earned_hours        = budget_hours * pct_installed
prod_factor         = earned_hours / actual_hours
hours_at_completion = actual_hours + (budget_hours - earned_hours) / prod_factor

Worked example detail

Cost code Budget hrs % installed Earned Actual Factor
Formwork 1,800 72% 1,300 1,500 0.87
Rebar 900 69% 620 600 1.03
Slab on grade 1,300 52% 680 1,000 0.68

Tables and fields

Table Fields Notes
timecards job_id, cost_code, crew_id, work_date, hours
quantities job_id, cost_code, work_date, qty, unit From field reports
budgets job_id, cost_code, budget_hours, budget_qty, unit

SQL sketch

WITH q AS (SELECT job_id, cost_code, SUM(qty) qty FROM quantities GROUP BY 1,2),
     t AS (SELECT job_id, cost_code, SUM(hours) hrs FROM timecards GROUP BY 1,2)
SELECT b.job_id, b.cost_code,
  b.budget_hours * q.qty / NULLIF(b.budget_qty,0) AS earned_hours, t.hrs AS actual_hours,
  (b.budget_hours * q.qty / NULLIF(b.budget_qty,0)) / NULLIF(t.hrs,0) AS prod_factor
FROM budgets b LEFT JOIN q USING (job_id, cost_code) LEFT JOIN t USING (job_id, cost_code);

Build spec

Copy this into a ticket. It lists the grain, inputs, logic, and edge cases.

metric: construction.labor_productivity
grain: one row per job per cost code per week
inputs:
  - budget_hours
  - budget_qty
  - qty_installed
  - actual_hours
logic:
  - earned_hours = budget_hours * qty_installed / budget_qty
  - factor = earned_hours / actual_hours
edge_cases:
  - no quantity reported: return null, not 0
  - actual_hours = 0: return null
  - unit mismatch: block and flag
  - qty over 100%: cap and flag for budget update

As a dashboard card

  • Bar per cost code with a 1.0 reference line, and a weekly trend for the largest codes.

Common mistakes

  • Joining timecards and quantities row by row, which double counts. Aggregate each first.
  • Using labor dollars instead of hours.
  • Showing a factor when quantities are missing.